铺设100级pe各类供水管道38.014km,其中:dn250pe(1.0mpa)长度971m,dn225pe(1.6mpa)长度6688m,dn225pe(1.25mpa)长度1987m,dn200pe(1.0mpa)长度8046m,dn180pe(1.6mpa)长度5377m,dn160pe(1.6mpa)长11584m,dn110pe(1.6mpa)长3360m.非开挖水平定向钻18907m;新建闸阀井39座;硬化道路拆除及恢复----;管道穿河(28处)共计1988m:工艺流程:定线开挖沟槽下管接口覆土试压
工程备注: 截止(2025年03月31日),该项目处于主体施工阶段